The Sioux Falls school board is moving forward with $45 million in construction projects at schools across the district.

The list includes 17 different schools, including Southeast Technical Institute. Eleven of the schools will see additional security upgrades.  At many schools, that requires expansion of the main entrance of the building and modifying the entrance access for increased security. 

The Southeast Technical Institute project will construct a new facility on the south end of campus. The facility will be approximately 75,000 square feet in size. It will house Automotive Technology, Diesel Technology, and Hospitality Management. It will also have an auditorium and administrative area. 

Source: Sioux Falls School Board Agenda

1. Southeast Technical Institute – Laboratory Building and Ed Wood Center Renovation Project

The project will construct a new facility on the south end of campus, the facility will be approximately 75,000 square feet in size. The facility will house Automotive Technology, Diesel Technology, and Hospitality Management. The facility will also have an auditorium and administrative area.

The project will also include the expansion/renovations of the Ed Wood facility for the Auto Collision program. The area of renovation will be space vacated by Auto Technology when they move to the new facility.

Southeast Technical Institute will fund the project with State Facility Bonding Funds.

Total estimated Project cost is approximately $18,000,000

2. Washington High School – CIP Addition and Renovation Project

The project will expand the main entrance of the school and modify the entrance access for increased security.

Total project estimated cost is approximately $550,000

3. Roosevelt High School – CIP Addition and Renovation Project

The project will expand the main entrance of the school and modify the entrance access for increased security.

Total project estimated cost is approximately $500,000

4. Axtell Park School – CIP Renovation Project

The project will provide the facility renovations necessary to accommodate the various programs being relocated to the Axtell Park building when the Middle School program moves to the new McGovern Middle School, spring 2014. The project will construct a new stair entrance on the northwest corner of the facility, construct additional restrooms, provide access control within the school for the various programs, provide multiple student drop-off areas, and construct additional parking on site. The project will also update several existing air-conditioning unit ventilators in the renovated areas.

Total project estimated cost is approximately $2,500,000

5. Patrick Henry Middle School – CIP Addition and Renovation Project

The project will expand the existing office area and modify the main entrance access. The project will include all remaining security items identified for Patrick Henry. The project will also renovate the existing special education restroom/changing area to meet today's ADA standards.

Total project estimated cost is approximately $750,000

6. Whittier Middle School – CIP Addition and Renovation Project

The project will expand the existing office area and modify the main entrance access. The project will include all remaining security items identified for Whittier. The project will also renovate the existing stage area into classrooms and modify the west service drive/dock and garbage area.

Total project estimated cost is approximately $850,000

7. Laura B Anderson Elementary – CIP Addition and Renovation Project

The project will relocate the existing administration area into the existing music classroom adjacent to the main entrance. This will allow the entrance modification of the main entrance per safe and secure recommendations. The project will then expand and renovate the existing administration area into 2 music classrooms. The project will also update one (1) existing boiler and implement the remaining security items identified for Laura B. Anderson.

Total project estimated cost is approximately $900,000

8. Terry Redlin Elementary – CIP Addition and Renovation Project

The project will expand the existing office area, provide an office for the nurse in the health area and modify the main entrance access. The project will include all remaining security items identified for Terry Redlin.

Total project estimated cost is approximately $360,000

9. Cleveland Elementary – CIP Renovation Project

The project will renovate the existing office area, provide an office for the nurse in the health area and modify the main entrance access. The project will include relocation of staff restrooms, renovation of 3 existing toilet rooms and all remaining security items identified for Cleveland.

Total project estimated cost is approximately $300,000

10.Garfield Elementary – CIP Addition and Renovation Project

The project will relocate the existing administration area into the existing staff workroom area and music classroom on the east side of the school. The project will construct a new main entrance on Elmwood Avenue. The project will then expand and renovate the existing administration area into 2 music classrooms and modify the existing entrance to separate the School and Community Center. The project will also update the existing boilers and implement the remaining security items identified for Garfield.

Total project estimated cost is approximately $1,500,000

11.Anne Sullivan Elementary – CIP Addition and Renovation Project

The project will expand the existing office area, and modify the main entrance per safe and secure recommendations. The project will include all remaining security items identified for Anne Sullivan.

Total project estimated cost is approximately $400,000

12.Hayward Elementary – CIP Addition and Renovation Project

The project will relocate the existing administration area into an existing classroom adjacent to the main entrance. This will allow the entrance modification of the main entrance per safe and secure recommendations. The project will then construct a new classroom on the north side of the school and modify the existing entrance to separate the School and Community Center.

Total project estimated cost is approximately $1,500,000

13.Hawthorne Elementary – CIP Addition and Renovation Project

The project will expand the existing office area, provide ADA health room and modify the main entrance access for both the School and school based Falls Clinic. The project will include all remaining security items identified for Hawthorne.

Total project estimated cost is approximately $1,000,000

14.Robert Frost Elementary – CIP Classroom Addition and Renovation Project

The project will construct 8 new classrooms to Robert Frost. The classrooms will provide space in the school for the District's Challenge Center which will be relocated from Garfield to Robert Frost.

The project will begin summer/fall 2014 with final completion scheduled for the fall of 2015.

Total project estimated cost is approximately $2,200,000

15.Discovery Elementary – CIP Classroom Addition and Renovation Project

The project will construct 10 classrooms, 1 art/music classroom, boy's & girl's restrooms, expand the existing multi-purpose room and expand an existing classroom for kindergarten. The additions will provide the space needed for the west-side growth identified in the District's boundary planning process.

The project will begin summer/fall 2014 with final completion scheduled for the fall of 2015.

Total project estimated cost is approximately $3,400,000

16.RF Pettigrew Elementary – CIP Classroom Addition and Renovation Project

The project will construct 8 classrooms, 3 early childhood classrooms, therapy room 1 art/music classroom, boy's & girl's restrooms, expand the existing multi-purpose room and expand an existing classroom for kindergarten. The additions will provide the space needed for the west-side growth identified in the District's boundary planning process.

The project will begin summer/fall 2014 with final completion scheduled for the fall of 2015.

Total project estimated cost is approximately $4,500,000

17.New Jefferson Elementary School Project – CIP

The project will construct a new 3-Section Elementary School on the Jefferson site, to house the District's Spanish Immersion Elementary School. The building design will be a modified reuse of the Susan B. Anthony Elementary building plan. The project will be approximately 73,000sf in size and will follow the District's Educational Specifications.

The building will be constructed on the north end of the Jefferson site. The new facility will combine the existing Rosa Parks and Robert Frost Immersion programs. The project will be coordinated with the City of Sioux Falls, looking at parking and drop off options for the school.

The project design will begin this spring with final design being completed fall of 2014. We anticipated bidding the project winter of 2014/15. The project will begin construction spring of 2015 with completion scheduled for August 2016 in time for the 2016–17 school year.

Estimated project cost: School $11,000,000

Furnishings & Equipment $ 900,000

  • Vikings to add another $1.2M to stadium project

    Vikings to add another $1.2M to stadium project

    Vikings to add another $1.2M to stadium project

    Saturday, April 19 2014 3:41 PM EDT2014-04-19 19:41:21 GMT
    MINNEAPOLIS (AP) - The Minnesota Vikings are contributing another $1.2 million to the new stadium to put in a bigger video board on the facility's west end and for other video-related upgrades.The funding was approved Friday by the Minnesota Sports Facilities Authority. It brings the total cost of the project from $975 million to $976.2 million.The team had initially agreed to contribute $477 million to the project. In November, the Vikings agreed to put up $26.4 million in contingency funds....More >>
    MINNEAPOLIS (AP) - The Minnesota Vikings are contributing another $1.2 million to the new stadium to put in a bigger video board on the facility's west end and for other video-related upgrades.The funding was approved Friday by the Minnesota Sports Facilities Authority. It brings the total cost of the project from $975 million to $976.2 million.The team had initially agreed to contribute $477 million to the project. In November, the Vikings agreed to put up $26.4 million in contingency funds....More >>
  • SD lottery offers losing tickets a second chance

    SD lottery offers losing tickets a second chance

    SD lottery offers losing tickets a second chance

    Saturday, April 19 2014 2:57 PM EDT2014-04-19 18:57:20 GMT
    PIERRE, S.D. (AP) - The South Dakota Lottery has announced a second chance game for players with losing scratch-off tickets.The program, called Play it Again, will launch next Wednesday. Members of the Lottery Players Club can enter non-winning tickets in an online drawing.Lottery executive director Norm Lingle says other states have similar games and gamers have asked for it in South Dakota. Lingle says second chance opportunities extend the length and value of games.The first game in the pr...More >>
    PIERRE, S.D. (AP) - The South Dakota Lottery has announced a second chance game for players with losing scratch-off tickets.The program, called Play it Again, will launch next Wednesday. Members of the Lottery Players Club can enter non-winning tickets in an online drawing.Lottery executive director Norm Lingle says other states have similar games and gamers have asked for it in South Dakota. Lingle says second chance opportunities extend the length and value of games.The first game in the pr...More >>
  • Railroad group says $1 million pledged locally

    Railroad group says $1 million pledged locally

    Railroad group says $1 million pledged locally

    Saturday, April 19 2014 2:53 PM EDT2014-04-19 18:53:21 GMT
    PIERRE, S.D. (AP) - A South Dakota organization that helps raise money for railroad rehabilitation says more than $1 million has been committed locally to help match a federal grant for which the state is applying.Rails to the Future says the state is seeking $12.6 million in a Transportation Investment Generating Economic Recovery (TIGER) grant. The state wants to rehab the state-owned railroad from Chamberlain to Presho.The entire project is estimated to cost $29 million. Earlier this month...More >>
    PIERRE, S.D. (AP) - A South Dakota organization that helps raise money for railroad rehabilitation says more than $1 million has been committed locally to help match a federal grant for which the state is applying.Rails to the Future says the state is seeking $12.6 million in a Transportation Investment Generating Economic Recovery (TIGER) grant. The state wants to rehab the state-owned railroad from Chamberlain to Presho.The entire project is estimated to cost $29 million. Earlier this month...More >>
  • Big Sioux Falls bar fight ends with three people in custody

    Big Sioux Falls bar fight ends with three people in custody

    Friday, April 18 2014 10:11 PM EDT2014-04-19 02:11:32 GMT
    Three men are in custody after a large bar fight in Sioux Falls.It happened Friday morning around 1 a.m. at Bigs Sports Bar on West 12th Street.Sioux Falls Police say when they arrived, there were an estimatedMore >>
    Three men are in custody after a large bar fight in Sioux Falls.More >>
  • Vice principal saved from Korea ferry found hanged

    Vice principal saved from Korea ferry found hanged

    Friday, April 18 2014 9:22 PM EDT2014-04-19 01:22:31 GMT
    Police say a high school vice principal who had been rescued from a sinking South Korean ferry has been found hanging from a tree. The news of the death came Friday as rescuers scrambled to find hundredsMore >>
    Police say a high school vice principal who had been rescued from a sinking South Korean ferry has been found hanging from a tree.More >>
  • Magnitude-7.2 earthquake shakes Mexican capital

    Magnitude-7.2 earthquake shakes Mexican capital

    Friday, April 18 2014 9:21 PM EDT2014-04-19 01:21:12 GMT
    A powerful magnitude-7.2 earthquake shook central and southern Mexico on Friday, sending panicked people into the streets. Some walls cracked and fell, but there were no reports of major damage or casualties. TheMore >>
    A powerful magnitude-7.2 earthquake shook central and southern Mexico on Friday, sending panicked people into the streets. Some walls cracked and fell, but there were no reports of major damage or casualties.More >>
  • Sherpa guides 'backbone' of Mount Everest expeditions

    Sherpa guides 'backbone' of Mount Everest expeditions

    Friday, April 18 2014 9:20 PM EDT2014-04-19 01:20:11 GMT
    Nepal's Sherpa guides know what it's like to be on top of the world. For more than six decades, the Sherpas have been the unsung heroes of Mount Everest climbing expeditions and have helped thousandsMore >>
    Nepal's Sherpa guides know what it's like to be on top of the world. More >>
  • Should you use self-defense to protect yourself?

    Should you use self-defense to protect yourself?

    Friday, April 18 2014 8:07 PM EDT2014-04-19 00:07:32 GMT
    The city's second murder for the year has some people worried about their protection.Many times women are attacked by someone they know.In the recent murder of a Sioux Falls woman, police say the suspectMore >>
    The city's second murder for the year has some people worried about their protection.Many times women are attacked by someone they know.In the recent murder of a Sioux Falls woman, police say the suspectMore >>
Powered by WorldNow
All content © Copyright 2000 - 2014 WorldNow and KSFY. All Rights Reserved.
For more information on this site, please read our Privacy Policy and Terms of Service or our EEO Report.